title: Sanctuary Sandringham – Construction Update (April 2025)
description: Sanctuary Sandringham construction progresses with major milestones in April, setting a strong foundation for the upcoming phases. Exciting updates expected in May. Stay tuned!
image: https://blog.norus.com.au/hubfs/Bay%20Road-4.jpg
---

[Skip to the main content.](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026#main-content)

[![Copy of NORUS BRANDING](https://blog.norus.com.au/hs-fs/hubfs/Norus%20Projects/Copy%20of%20NORUS%20BRANDING.png?width=500&height=125&name=Copy%20of%20NORUS%20BRANDING.png "Copy of NORUS BRANDING")](https://www.norus.com.au)

[![Copy of NORUS BRANDING (1)](https://blog.norus.com.au/hs-fs/hubfs/Copy%20of%20NORUS%20BRANDING%20(1).png?width=500&height=125&name=Copy%20of%20NORUS%20BRANDING%20(1).png "Copy of NORUS BRANDING (1)")](https://www.norus.com.au)

- [Projects](https://www.norus.com.au/sanctuary_sandringham) 
    - [Norus | Beach Point](https://www.norus.com.au/beach_point)
    - [Norus | Parkview](https://www.norus.com.au/park_view)
    - [Norus | Riverbend](https://www.norus.com.au/riverbend_ivanhoe)
    - [Norus | Sanctuary Sandringham](https://www.norus.com.au/sanctuary_sandringham)
- [About](https://www.norus.com.au/about)
- [Construction Updates](https://www.norus.com.au/construction_progress)
- [Completed Projects](https://www.norus.com.au/completed_projects)
- [Blog](https://blog.norus.com.au)

Toggle Menu

Toggle Menu

- [Projects *Toggle Menu*](https://www.norus.com.au/sanctuary_sandringham) 
    - [Norus | Beach Point](https://www.norus.com.au/beach_point)
    - [Norus | Parkview](https://www.norus.com.au/park_view)
    - [Norus | Riverbend](https://www.norus.com.au/riverbend_ivanhoe)
    - [Norus | Sanctuary Sandringham](https://www.norus.com.au/sanctuary_sandringham)
- [About](https://www.norus.com.au/about)
- [Construction Updates](https://www.norus.com.au/construction_progress)
- [Completed Projects](https://www.norus.com.au/completed_projects)
- [Blog](https://blog.norus.com.au)

[*Facebook*](https://www.facebook.com/profile.php?id=61554483013407) [*Instagram*](https://www.instagram.com/norus.projects/) [*LinkedIn*](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026#0) [*Twitter*](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026#0) [*Youtube*](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026#0) [*Medium*](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026#0)

 1 min read

# Sanctuary Sandringham – Construction Update (April 2025)

[Norus Blog](https://blog.norus.com.au/author/norus-blog) : Published April 30, 2025

[Project Update](https://blog.norus.com.au/tag/project-update) [building update](https://blog.norus.com.au/tag/building-update) [Sanctuary Sandringham](https://blog.norus.com.au/tag/sanctuary-sandringham)

![Sanctuary Sandringham – Construction Update (April 2025)](https://blog.norus.com.au/hubfs/Bay%20Road-4.jpg)

We’re excited to share the latest construction progress at *Sanctuary Sandringham*.

April was a strong month on-site, with several major milestones achieved. The basement footings were completed, providing a solid foundation for the structure above. Following this, the first half of the basement 2 slab was poured and the first half of the basement 2 precast panels were installed, starting to bring real shape to the lower levels of the building. In addition, formwork for the suspended slab on basement 1 commenced, setting the stage for the next phase of construction. 

 

![Bay Road-1](https://blog.norus.com.au/hs-fs/hubfs/Sanctuary%20Sandringham/Construction%20Update%20Photos/SS%20April%202025/Bay%20Road-1.jpg?width=4027&height=3020&name=Bay%20Road-1.jpg)

 

Looking ahead, May promises to be another busy month as key structural works continue. We’re on track to complete the full basement 2 slab and the remaining basement 2 precast panels. The basement 1 slab will also be poured, and the basement 1 precast panels will be installed, continuing the upward momentum of the build. Excitingly, works will also commence on forming the ground floor slab, a major milestone as the project begins to rise above ground level.

 

![Bay Road-7](https://blog.norus.com.au/hs-fs/hubfs/Sanctuary%20Sandringham/Construction%20Update%20Photos/SS%20April%202025/Bay%20Road-7.jpg?width=4027&height=3020&name=Bay%20Road-7.jpg)

 

With construction advancing steadily, *Sanctuary Sandringham* is well on its way to becoming one of Bayside’s most sought-after new addresses. We look forward to bringing you more updates as we progress through the coming months.

### Register Your Interest In Norus Projects Apartments and Townhouses.

Just enter your details below.

Loading...

 

 

 

The information provided on our website, blogs, social media, and any affiliated websites, is general information from opinions generated from research, information and personal experiences pertaining to the relevant topic. They are intended to provide insights and information on the related topics and not provided to be the entire source of information for individuals. Individuals are encouraged to source further information from real estate professionals and affiliates. Information should not be regarded as legal or real estate advice. The materials are provided for informational purposes only and do not constitute legal advice or should not be solely relied upon for legal advice. Every effort is made to ensure the information is reliable and up to date.

- [Tweet](https://twitter.com/share)

[![Sanctuary Sandringham Construction Update (Feb 2025).](https://blog.norus.com.au/hubfs/Sanctuary%20Sandringham/Construction%20Update%20Photos/SS%20Feb-4.jpg)](https://blog.norus.com.au/sanctuary-sandringham-construction-update-march-2025)

#### [Sanctuary Sandringham Construction Update (Feb 2025).](https://blog.norus.com.au/sanctuary-sandringham-construction-update-march-2025)

[Norus Blog](https://blog.norus.com.au/author/norus-blog) : Mar 7, 2025, 1:41:00 PM

Exciting progress at Sanctuary Sandringham with major excavation milestones achieved and upcoming structural works set to enhance this premium...

[Project Update](https://blog.norus.com.au/tag/project-update) [building update](https://blog.norus.com.au/tag/building-update) [Sanctuary Sandringham](https://blog.norus.com.au/tag/sanctuary-sandringham)

[Find Out More Details](https://blog.norus.com.au/sanctuary-sandringham-construction-update-march-2025)

[![Sanctuary Sandringham Construction Update (March 2025)](https://blog.norus.com.au/hubfs/1-Apr-09-2025-02-41-29-6094-AM.png)](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2025)

#### [Sanctuary Sandringham Construction Update (March 2025)](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2025)

[Norus Blog](https://blog.norus.com.au/author/norus-blog) : Apr 9, 2025, 3:30:00 AM

Sanctuary Sandringham's construction progresses with the completion of bulk excavation and the installation of a tower crane, marking the start of...

[Project Update](https://blog.norus.com.au/tag/project-update) [building update](https://blog.norus.com.au/tag/building-update) [Sanctuary Sandringham](https://blog.norus.com.au/tag/sanctuary-sandringham)

[Find Out More Details](https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2025)

[![Beach Point Sandringham – Construction Update (Feb 2025)](https://blog.norus.com.au/hubfs/Beach%20Road-2.jpg)](https://blog.norus.com.au/beach-point-sandringham-construction-update-march-2025)

#### [Beach Point Sandringham – Construction Update (Feb 2025)](https://blog.norus.com.au/beach-point-sandringham-construction-update-march-2025)

[Norus Blog](https://blog.norus.com.au/author/norus-blog) : Mar 7, 2025, 12:32:00 PM

Exciting progress at Beach Point Sandringham: major milestones achieved, structural work begins and the project transitions to above-ground...

[Project Update](https://blog.norus.com.au/tag/project-update) [building update](https://blog.norus.com.au/tag/building-update) [Beach Point Sandringham](https://blog.norus.com.au/tag/beach-point-sandringham)

[Find Out More Details](https://blog.norus.com.au/beach-point-sandringham-construction-update-march-2025)

- [Privacy Policy](https://www.norus.com.au/privacy_policy)

© 2026 Norus Projects

[*Facebook*](https://www.facebook.com/profile.php?id=61554483013407)[*Instagram*](https://www.instagram.com/norus.projects/)

*Return to Top*

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Norus Blog",
    "url" : "https://blog.norus.com.au/author/norus-blog"
  },
  "dateModified" : "2025-04-30T01:47:08.608Z",
  "datePublished" : "2025-04-30T01:47:08.000Z",
  "headline" : "Sanctuary Sandringham – Construction Update (April 2025)",
  "image" : [ "https://blog.norus.com.au/hubfs/Bay%20Road-4.jpg" ],
  "mainEntityOfPage" : {
    "@id" : "https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://blog.norus.com.au/hubfs/3%20(10)-1.png"
    },
    "name" : "Franky Pty. Ltd. ATF Franky Trust"
  }
}
```

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : [ {
    "@type" : "Person",
    "name" : "Norus Blog",
    "url" : "https://blog.norus.com.au/author/norus-blog"
  } ],
  "dateModified" : "2025-04-30T01:47:08Z",
  "datePublished" : "2025-04-30T01:47:08Z",
  "description" : "Sanctuary Sandringham construction progresses with major milestones in April, setting a strong foundation for the upcoming phases. Exciting updates expected in May. Stay tuned!",
  "headline" : "<span id=\"hs_cos_wrapper_name\" class=\"hs_cos_wrapper hs_cos_wrapper_meta_field hs_cos_wrapper_type_text\" style=\"\" data-hs-cos-general-type=\"meta_field\" data-hs-cos-type=\"text\" >Sanctuary Sandringham – Construction Update (April 2025)</span>",
  "image" : [ "https://4298067.fs1.hubspotusercontent-na1.net/hubfs/4298067/Bay%20Road-4.jpg" ],
  "inLanguage" : "en-au",
  "keywords" : "Project Update, building update, Sanctuary Sandringham",
  "mainEntityOfPage" : {
    "@id" : "https://blog.norus.com.au/sanctuary-sandringham-construction-update-april-2026",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "name" : "Norus Projects"
  }
}
```