August has brought a real step change at Riverbend Ivanhoe, with the building now climbing steadily and multiple trades working in parallel across several levels at once. What was once a site defined by basement works and ground floor framing is now taking on the unmistakable shape of an apartment building and the pace of progress this month reflects that shift.

 

Structure climbing level by level

The standout achievement this month is the completion of the level 2 and level 3 slabs, with over 1000 cubic metres of concrete poured to bring both levels to life. Alongside the slabs, precast panel installation has also progressed strongly across levels 2 and 3, with roughly 70 columns and 21 panels now in place, forming the structural backbone that will carry the building through its next stages.

With momentum firmly behind the team, attention is now turning to level 4, with the slab scheduled to be poured in the coming week. Each pour brings the building noticeably closer to its full height and marks another step in the steady rhythm the construction team has maintained throughout the build.

Framing is also well underway, with light gauge steel now being installed for apartments on level 2 east and level 3 west. This work is laying the internal framework for what will soon become liveable spaces and it's a stage where the building really starts to reveal its final form. The roofing works are set to commence in the coming week, adding another layer of protection and progress to the build as it continues to rise.

Finishes taking hold on the ground floor

While the upper levels push skyward, the work on the ground floor is moving into a more detailed and finished phase. The internal and external walls of the ground floor east apartments have now been framed, with sheeting around 30% complete. The rough-in works for plumbing and electrical are set to commence in the coming week, bringing these apartments another step closer to completion.

Windows are also progressing well, with 50% now installed across the ground floor. High-level services have been completed throughout the ground floor apartments and corridors, forming an essential part of the building's infrastructure ahead of final fit-out. Looking ahead, external wall sheeting is set to commence mid-August, further advancing the finished look and feel of the ground floor.

A building taking real shape

From concrete slabs and precast panels to framing, roofing and finishes, August has been a month where Riverbend Ivanhoe's progress has become impossible to miss. Every level poured and every wall framed brings this Ivanhoe address closer to completion and closer to the moment residents can finally call it home.

For more information about Riverbend Ivanhoe or to enquire about available residences, contact the sales team to book your private appointment at the display suite or register your interest using the form below.

 

 

 

*Terms and Conditions apply to any promotions and information that may be contained within this communication. Promotions may end at any time without notice and at a maximum will not be available for more than 14 days from the date of commencement. Only one promotion can be used per purchase and can not be used in conjunction with any other promotions. Prices and other values and information may change at any time without notice. For any government grants, concessions, programs, taxes, levies or duties, please refer to the relevant government websites for further information. The information contained herein is given for general information purposes only and it is subject to change. Readers, viewers and consumers are advised to perform their own research and investigations and obtain their own financial, legal and other advice. The information and materials do not form any representation by any vendors or agents of any vendors and may include third-party opinions that do not represent the opinion of any vendor or agent. They do not form part of any contract of sale and they do not constitute legal, financial, real estate or other advice and must not be regarded or relied upon as such. No warranty is given either expressly or implied and the vendors or agents do not assume liability for negligence or otherwise with respect to the contents herein. All images are artist impressions only. Any plans are yet to have had their structural and services review so are subject to change prior to completion of construction. All plans, dimensions, areas and particulars herein whether by measurements or visual representation are approximate only, for general information only, and do not constitute any representation by the vendor or its agents or representatives. They do not form part of any contract of sale. Changes will undoubtedly be made during development and dimensions, fittings, finishes and specifications are therefore subject to change. Any furniture, goods and chattels depicted in this document are not included with any sale. Prospective purchasers or lessees are advised to not to rely on the information contained herein and to satisfy themselves as to the accuracy of all information given by making their own inspections, searches, inquiries and advises or as is otherwise necessary. The vendor or its agents or representatives will not be responsible for any error or misdescription which may appear. Further, the vendor or the developer or their agents or representatives do not represent, warrant and/or guarantee that the integrity of this communication has been maintained or that the communication is free of errors, virus, interception or interference. Usage of this or any other websites and materials and any associated website or material is subject to further terms and conditions. Further terms and conditions apply. Please enquire with the vendor and agent for further terms and conditions.