We’re excited to share the latest construction milestone at our Beach Rd site in Sandringham. 

Works are progressing well, with significant achievements both below ground and in preparation for the structure above.

All basement footings and in-ground plumbing have been successfully completed, marking a major step forward in the build. The basement 2 slab has been poured, providing a solid foundation for the construction of the superstructure.

 

Screenshot 2025-04-09 at 1.07.33 pm

 

Formwork for basement 1 is now underway, with the first section of the slab scheduled to be poured shortly. The ramp connecting basement 1 to basement 2 on the southern side of the site has also been poured, further advancing access and functionality at this level.

 

Screenshot 2025-04-09 at 1.07.53 pm

 

Precast installation has commenced, with all columns and panels for basement 2 now in place. With these milestones reached, the structural component of the build is set to ramp up, with major concrete pours planned approximately every 10 days moving forward.

Construction will continue following a consistent sequence involving formwork, steel reinforcement, post-tensioning, concrete pours and ongoing precast panel installation.

 

Screenshot 2025-04-09 at 1.09.56 pm

 

The team is proud of the momentum achieved so far and remains focused on maintaining progress throughout the next stages of the project. Further updates will be shared as construction continues to evolve.

Only a select few apartments remain in this exclusive bayside development, including the final 2-bedroom, 2-bathroom plus study residence.
2 bedroom apartment prices start from $925,000, 3 bedroom from $1,695,000 and luxurious 4 bedrooms from $3,955,000. 

Buyers who purchase off the plan may also benefit from generous stamp duty savings - but only for a limited time.

To arrange a private appointment or to learn more, get in touch with our team today or simply fill out the form below.

Register Your Interest In Norus Projects Apartments and Townhouses.

Just enter your details below.

 

The information provided on our website, blogs, social media, and any affiliated websites, is general information from opinions generated from research, information and personal experiences pertaining to the relevant topic. They are intended to provide insights and information on the related topics and not provided to be the entire source of information for individuals. Individuals are encouraged to source further information from real estate professionals and affiliates. Information should not be regarded as legal or real estate advice. The materials are provided for informational purposes only and do not constitute legal advice or should not be solely relied upon for legal advice. Every effort is made to ensure the information is reliable and up to date. 

Beach Point Sandringham – Construction Update (Feb 2025)

Beach Point Sandringham – Construction Update (Feb 2025)

Exciting progress continues at Beach Point Sandringham, with significant milestones achieved in the first few months of the year. Located on Beach...

Find Out More Details
Sanctuary Sandringham Construction Update (March 2025)

Sanctuary Sandringham Construction Update (March 2025)

Construction at Sanctuary Sandringham continues to move forward with great momentum. The project has reached several key milestones that pave the way...

Find Out More Details
Sanctuary Sandringham Construction Update (Feb 2025).

Sanctuary Sandringham Construction Update (Feb 2025).

As we move further into 2025, construction at Sanctuary Sandringham, located on Bay Road in Sandringham, is progressing steadily. With work well...

Find Out More Details